A Sheenstar apple juice production line has been commissioned at the customer’s factory for 790 ml bottled apple juice. The project covers the process from fresh fruit preparation through filling and HPP cold sterilization, followed by conveying, labeling, and packaging.

From fresh apples to packed bottles

The line begins with fresh fruit cleaning. The apples then move through crushing and pressing so the juice can be prepared for the next production stages. Blending follows before the product reaches the filling machine.

After filling, the bottled apple juice goes through HPP ultra-high-pressure cold sterilization. The downstream process then conveys the bottles to labeling and packaging. By connecting these stages, the line gives the customer one production route for its 790 ml apple juice rather than a stand-alone filler with separate, uncoordinated handling.

Each stage has a different task, but the product must move through them as one continuous project. The container format, filling method, sterilization process, and final packaging all need to suit the same apple juice. Commissioning at the customer’s site confirms the way these parts work together under actual factory conditions.

Why this line uses weighing filling

The filling machine measures the product by actual weight. Weight sensors monitor the amount entering the bottle, and the machine stops discharging when the set weight is reached. This differs from a volumetric system, which uses product volume as the basis for filling.

That distinction is useful for this apple juice application because the material may contain bubbles. Bubbles can make the apparent volume look greater even when the true product amount is lower. A volumetric method can therefore stop after reaching a volume that includes part of that trapped air.

Weighing filling is not affected by the apparent volume created by bubbles in the same way. The system follows the measured weight and ends the fill when it reaches the set value. This gives the operator direct control over the true filling weight of the product in each bottle.

The method is easy to understand on the production floor. The target is entered as a weight, the sensor measures the bottle during filling, and discharge stops at the set point. For a product where bubbles can disturb a volume reading, that measurement basis addresses a practical filling problem.

Commissioning the complete process at the customer site

A production line is not finished when the machines leave the manufacturing workshop. The equipment must be installed in the customer’s factory, connected as a line, adjusted for the product and packaging, and checked during operation.

For this project, Sheenstar arranged engineers to install the equipment and commission the line. The work also included training for the customer’s relevant operators. That training supports correct use and routine maintenance after the engineers complete the site work.

Operator involvement is important during commissioning because the customer team will run the equipment every day. They need to understand the sequence from fruit preparation to packing, the filling settings, and the basic maintenance requirements of the line. Training at the installed equipment keeps those discussions connected to the customer’s real production setup.

A production line built around the product

This project combines three clearly defined requirements. The product is apple juice made from fresh fruit. The package is a 790 ml bottle. The filling method uses weight sensors so bubbles do not lead to an uncontrolled true weight.

The HPP cold sterilization stage is also part of the planned process, so it sits between filling and the later conveying, labeling, and packaging steps. Keeping the full sequence in view helps the project team coordinate the equipment around the customer’s finished bottle.

The commissioned line now gives the customer a complete route for producing its bottled apple juice. It begins with fruit cleaning and pressing, uses weighing filling for the 790 ml package, continues through HPP cold sterilization, and finishes with the downstream packaging operations.

Producers planning a similar line can contact Sheenstar with their juice, bottle size, filling requirement, and intended process. Those details allow the engineering team to discuss a suitable production arrangement and the service needed for installation, commissioning, and operator training.

The customer’s line also shows why the filling method should be discussed together with the product process. Fresh fruit preparation creates the apple juice, weighing filling controls the amount in the bottle, and HPP cold sterilization follows after filling. Conveying, labeling, and packaging complete the route. The 790 ml bottle passes through a line whose main stages were selected as parts of the same production plan.