A filling line site is ready when the latest layout is approved, the building can receive and support the equipment, every utility has a defined connection and acceptance test, and the installation team can work without waiting for access, tools, or cross-trade decisions.
Finish with a joint walkdown before delivery. The supplier’s approved drawings and data sheets set the machine-specific values. Local engineers remain responsible for the building, electrical installation, food-safety controls, lifting plan, and workplace requirements that apply at the destination.
1. Freeze the line boundary and drawing revisions
Start by marking where the supplier’s scope ends and the owner’s scope begins. Put that boundary on the process flow, machine list, and general arrangement. Include upstream product preparation, the filling block, conveyors, coding, labeling, packing, and any owner-supplied equipment.
Keep one drawing register with the title, revision, issue date, review status, and approver. Contractors should work from the same controlled package. A late machine move can affect anchors, drains, cable routes, conveyor elevations, and maintenance access, so every revision needs an impact note and a named owner.
| Record | Question it answers | Evidence before site work |
|---|---|---|
| Machine and scope list | Which equipment is supplied, owner-provided, or excluded? | Approved list with an interface owner |
| General arrangement | Where are machine footprints, operators, and service zones? | Signed layout with revision number |
| Utility connection drawing | Where does each service terminate? | Coordinates, sizes, loads, and connection details |
| Drawing register | Is every contractor using the current issue? | Controlled register distributed to all trades |
2. Check the building, floor, and maintenance clearances
Measure the finished building, not only the architectural drawing. Confirm column positions, wall openings, door widths, ceiling height, mezzanines, crane beams, lighting, ventilation ducts, and any pipework that enters the machine zone.
A qualified local engineer should confirm that the slab and foundations can support static loads, operating loads, vibration, and concentrated anchor forces. Record floor level and slope across the installation footprint. Correct high spots, weak areas, cracks, and drainage falls before machinery arrives.
Review working clearances with guards and cabinet doors fully open. Leave space to remove motors, filters, pumps, valves, fillers, and other service parts. Emergency exits and operator routes must remain clear after platforms, cable trays, and utility drops are installed.

3. Plan the delivery route before the truck arrives
Trace every machine from the unloading point to its final position. Check gate width, turning radius, road capacity, dock height, door openings, corridor width, overhead obstructions, floor loading, and the space needed to rotate long frames.
Compare the route with the supplier’s shipping list and packing dimensions. Identify which crates can travel intact and which must be unpacked outside the production area. Protect finished floors and hygienic zones, and provide a dry, secure staging area where packages can be sorted in installation sequence.
| Route check | Information required | Release evidence |
|---|---|---|
| External access | Vehicle size, axle load, turning and waiting space | Approved truck route and delivery window |
| Building entry | Clear door width and height, thresholds, ramps | Measured opening larger than the packed load |
| Internal movement | Aisles, corners, overhead services, floor capacity | Marked route and protection plan |
| Lifting | Load weight, center of gravity, lifting points | Approved lift plan and certified equipment |
Assign unloading leadership before the delivery date. Confirm the crane, forklift, skates, spreader beams, slings, operators, banksmen, and exclusion barriers. The lifting equipment must be suitable for the heaviest package and the least favorable reach.
4. Build one utility interface schedule
Combine electrical power, compressed air, process water, treated water, steam, cooling, carbon dioxide, drainage, ventilation, and communication services in one schedule. For every connection, state the required capacity, quality, pressure or voltage, connection size, physical location, responsible party, and test method.
Do not size plant services from line speed alone. Use the supplier’s approved utility data for normal production, maximum simultaneous demand, startup, cleaning, and sterilization where applicable. Check distribution losses and the demand from other factory users.
| Utility | Define before installation | Typical readiness check |
|---|---|---|
| Electrical power | Voltage, frequency, phase, load, protection, earthing | Measure voltage and phase condition at the machine point |
| Compressed air | Pressure, peak flow, filtration, dew point, oil class | Record pressure and quality under representative demand |
| Water | Quality, pressure, flow, temperature, storage | Sample and measure at the agreed connection |
| Steam or hot water | Pressure, peak duty, purity, condensate route | Warm-up and capacity test with safe discharge |
| Cooling | Supply/return temperature, flow, pressure, heat load | Confirm performance at design ambient conditions |
| CO2 | Food-grade specification, pressure, flow, ventilation | Leak test, detector check, and alarm response |
End each service at the agreed interface, cap or protect it from contamination, and label its isolation point. Flush and clean new piping where required. A reading at the central plant is not evidence that the service is acceptable at the machine connection.
5. Resolve drainage and hygiene zones before anchoring
Map where rinse water, product loss, cleaning solution, and floor-wash water will go. Confirm drain capacity, floor falls, trapped connections, wastewater separation, and any treatment required before discharge.
Coordinate drain positions with machine feet and anchors. A small layout change can leave a drain beneath a baseplate or force hoses across operator routes. Review the finished drainage plan with production, engineering, and food-safety personnel before drilling begins.
Define hygiene zones and the movement of people, packaging, ingredients, chemicals, waste, and maintenance tools. Choose cleanable wall and floor finishes and seal penetrations against pests and moisture. Keep utilities accessible without creating ledges, unsealed openings, or difficult-to-clean dead spaces.
6. Assign safety responsibilities before energization
Installation involves lifting, work at height, temporary electrical supplies, hot work, pressure testing, and several contractors working together. The site owner and installation companies should agree who controls each hazard and who can authorize energization.
Complete task risk assessments, permits, isolations, and emergency arrangements before work begins. Identify exclusion zones and safe pedestrian routes. Confirm that guards, platforms, stairs, handrails, and emergency stops can be installed without conflict with building services.
| Activity | Named control owner | Minimum evidence |
|---|---|---|
| Unloading and lifting | Site lifting coordinator | Lift plan, certifications, briefing, exclusion zone |
| Electrical energization | Authorized electrical person | Inspection, test results, isolation and release record |
| Pressure and utility testing | Utility system owner | Test procedure, calibrated instruments, safe discharge |
| Machine startup | Commissioning leader | Guard check, personnel clearance, startup authorization |
Nominate one person to control lockout and tagout across the installation. No utility should be connected or energized simply because construction is complete; it must be released through the agreed handover process.
7. Prepare people, documents, and commissioning materials
Confirm the installation and commissioning team, shift pattern, site induction, working hours, language support, accommodation, transport, and daily coordination meeting. Name one owner for each open site item so questions do not wait between departments.
Prepare the current drawings, manuals, electrical diagrams, software backups, certificates, inspection forms, and supplier contact list. Make controlled electronic copies available at the work area and record every approved field change for the final as-built package.
Commissioning also needs suitable containers, closures, labels, packaging film, lubricants, cleaning chemicals, product ingredients, laboratory materials, and safe waste-disposal capacity. Confirm specifications and quantities early enough to avoid completing the machinery installation with nothing available for testing.
8. Complete a joint site-readiness walkdown
Several days before dispatch or mobilization, walk the route and machine footprint with representatives from the owner, supplier, civil contractor, electrical contractor, utility contractor, production, and safety team. Use the latest drawing rather than memory.
Photograph each unloading area, access restriction, machine position, and utility interface. Record every open item with an owner, due date, and evidence required for closure. Separate genuine delivery blockers from work that can safely continue in parallel.
- Building, floor, foundations, and drainage released;
- delivery route, lifting plan, and staging area released;
- machine layout and utility connection points marked;
- temporary and permanent services safely available;
- materials, tools, welfare, security, and waste routes ready;
- permits, isolations, emergency contacts, and communication channels agreed.
Issue a signed readiness report after the walkdown. If a critical item remains open, record the recovery plan and its effect on shipment or installation rather than relying on a verbal promise.
9. Define each handover before site acceptance testing
Installation completion, mechanical completion, energization, dry commissioning, wet commissioning, performance testing, training, and final acceptance are different milestones. Define the entry criteria, responsible parties, records, and approval for each one.
| Milestone | Typical release criteria | Acceptance record |
|---|---|---|
| Mechanical completion | Equipment positioned, leveled, anchored, guarded, and inspected | Mechanical completion checklist |
| Ready to energize | Electrical tests complete, isolations controlled, personnel clear | Electrical release certificate |
| Ready for wet testing | Utilities proven, drains available, hygienic cleaning complete | Utility and sanitation release |
| Site acceptance test | Agreed product, package, duration, speed, and quality criteria available | Signed SAT protocol with results and open items |
| Production handover | Training complete, documents delivered, residual risks accepted | Handover certificate and punch-list ownership |
The final handover package should include approved drawings, as-built changes, inspection and test records, equipment manuals, software backups, spare-parts lists, training records, and a controlled punch list. Agree warranty start conditions and the route for technical support.
A site-preparation checklist is complete only when every critical interface has been inspected and measured. That evidence lets the installation team begin safely, reduces avoidable delays, and gives both the plant and equipment supplier a clear basis for commissioning and acceptance.